Quick answer: Bid post-construction cleaning by estimating labor-hours for each phase (rough clean, final clean and touch-up), multiplying by your loaded labor rate, adding materials, disposal, equipment and transport, then dividing by one minus your target margin. A 50-hour job with $430 of materials and equipment bids at $2,440 at a 25% margin.
Why are construction cleans so easy to underbid?
Construction cleans are easy to underbid because bidders price the final clean they can picture and forget the other two trips. The rough clean happens while trades are still working. The touch-up comes after the punch list, often on short notice. Each phase is a separate visit with its own setup and travel.
What happens in each phase?
- Rough clean. Debris removal, sweeping and heavy dust, so trades can finish.
- Final clean. Detailed cleaning of every surface, fixture, window, cabinet, vent and floor, plus sticker and residue removal.
- Touch-up. A return visit after trades fix punch-list items, before handover or inspection.
How do you calculate the bid?
Step 1. Estimate hours for each phase
Walk the site. Estimate rough, final and touch-up hours separately, using past jobs of the same type.
Step 2. Price the labor
Labor = total hours × loaded labor rate.
Step 3. Add materials and disposal
Chemicals, blades, bags, HEPA filters, protective coverings, and any dumpster or haul-away fees you’re responsible for.
Step 4. Add equipment and transport
Lifts, ladders, HEPA vacuums, floor machines, trailer and fuel.
Step 5. Set the price by margin
Bid = total cost ÷ (1 − target margin).
Example
Sample figures only.
| Item | Value |
|---|---|
| Rough / final / touch-up hours | 18 / 24 / 8 |
| Total labor-hours | 50 |
| Labor at $28/hour | $1,400 |
| Materials and disposal | $250 |
| Equipment and transport | $180 |
| Total cost | $1,830 |
| Bid at 25% margin | $2,440 |
| Gross profit | $610 |
What should the bid state in writing?
- Who removes construction debris and supplies the dumpster
- How extra trips caused by schedule changes are billed
- Which areas and surfaces are included and excluded
- Insurance, safety training and lift certification you’ll provide
What documents will a general contractor ask for?
Expect a certificate of insurance naming the GC, proof of workers’ compensation coverage, and a signed subcontract. In the US, add a W-9 and possibly OSHA training records and lien waivers. In Canada, expect a WSIB or provincial WCB clearance certificate. Price any extra insurance or training into the bid.
Price your project
Use the Post-Construction Cleaning Bid Calculator.
Related: Cleaning Equipment Cost Per Hour Calculator · How to Size a Cleaning Crew
Make the numbers easier
Explore free calculators for cleaning time, staffing, bids and supplies.
Browse calculators