How to Bid Post-Construction Cleaning

Quick answer: Bid post-construction cleaning by estimating labor-hours for each phase (rough clean, final clean and touch-up), multiplying by your loaded labor rate, adding materials, disposal, equipment and transport, then dividing by one minus your target margin. A 50-hour job with $430 of materials and equipment bids at $2,440 at a 25% margin.

Why are construction cleans so easy to underbid?

Construction cleans are easy to underbid because bidders price the final clean they can picture and forget the other two trips. The rough clean happens while trades are still working. The touch-up comes after the punch list, often on short notice. Each phase is a separate visit with its own setup and travel.

What happens in each phase?

  • Rough clean. Debris removal, sweeping and heavy dust, so trades can finish.
  • Final clean. Detailed cleaning of every surface, fixture, window, cabinet, vent and floor, plus sticker and residue removal.
  • Touch-up. A return visit after trades fix punch-list items, before handover or inspection.

How do you calculate the bid?

Step 1. Estimate hours for each phase

Walk the site. Estimate rough, final and touch-up hours separately, using past jobs of the same type.

Step 2. Price the labor

Labor = total hours × loaded labor rate.

Step 3. Add materials and disposal

Chemicals, blades, bags, HEPA filters, protective coverings, and any dumpster or haul-away fees you’re responsible for.

Step 4. Add equipment and transport

Lifts, ladders, HEPA vacuums, floor machines, trailer and fuel.

Step 5. Set the price by margin

Bid = total cost ÷ (1 − target margin).

Example

Sample figures only.

ItemValue
Rough / final / touch-up hours18 / 24 / 8
Total labor-hours50
Labor at $28/hour$1,400
Materials and disposal$250
Equipment and transport$180
Total cost$1,830
Bid at 25% margin$2,440
Gross profit$610

What should the bid state in writing?

  • Who removes construction debris and supplies the dumpster
  • How extra trips caused by schedule changes are billed
  • Which areas and surfaces are included and excluded
  • Insurance, safety training and lift certification you’ll provide

What documents will a general contractor ask for?

Expect a certificate of insurance naming the GC, proof of workers’ compensation coverage, and a signed subcontract. In the US, add a W-9 and possibly OSHA training records and lien waivers. In Canada, expect a WSIB or provincial WCB clearance certificate. Price any extra insurance or training into the bid.

Price your project

Use the Post-Construction Cleaning Bid Calculator.

Related: Cleaning Equipment Cost Per Hour Calculator · How to Size a Cleaning Crew

Make the numbers easier

Explore free calculators for cleaning time, staffing, bids and supplies.

Browse calculators

Explore all cleaning calculators

Find the right tool for bids, cleaning time, supplies, staffing and equipment.

Browse all calculators